The Month of October

This slideshow requires JavaScript.

First Week of October 2013

The preparation tank foundation has been finished and will be soon walled. The hydrolyzer tank has also been worked on having a regulated vent now and a cover to make it fully sealed when finished.

This slideshow requires JavaScript.

Second Week of October 2013

The Hydrolyzer tank top has a impermeable layer sealed to it to help it get to the fully sealed stage. It also starts to be “spun “ up like the Anaerobic tank. While this is happening more pex tubing is wrapped around the walls to help create a incubating environment.

This slideshow requires JavaScript.

Third Week of October 2013

The hydrolyzer tank has reached its max height. A ladder has been constructed on its West side to allow easy access to the roof. On the other side of the site towards the north the digestate storage tank is starting to be built.